Purchase Orders
Create and manage purchase orders to streamline your procurement workflow with suppliers.
Purchase Orders (POs) are formal requests sent to suppliers for goods or materials. They establish a clear record of what you ordered, at what price, and when you expect delivery — forming the first step in a traceable procurement cycle.
Creating a purchase order
- 1
Navigate to Purchase Orders
Go to Procurement → Procurement Hub → Purchase Orders from the sidebar.
- 2
Click Create PO
Click the Create PO button to start a new purchase order.
- 3
Select the supplier
Choose the supplier you are ordering from. The supplier’s contact details and payment terms will be pulled from their record automatically.
- 4
Add line items
Add the products or materials you want to order. For each line item, enter:
- Item — The product or material being ordered.
- Quantity — How many units you need.
- Expected unit price — The agreed or expected price per unit.
The total for each line item is calculated automatically.
- 5
Set the delivery date
Set the expected delivery date so you and the supplier have a shared understanding of when goods should arrive.
- 6
Submit
Click Submit to finalise the purchase order. The PO is assigned a unique reference number and can be sent to the supplier.
Purchase order creation form with supplier selection and line items
PO lifecycle and statuses
Purchase orders move through the following statuses:
- Draft — The PO is being prepared and has not been submitted yet.
- Submitted — The PO has been finalised and sent (or is ready to be sent) to the supplier.
- Partially Received — Some of the ordered items have been delivered, but not all.
- Fully Received — All ordered items have been delivered and recorded via a Goods Received Note.
- Cancelled — The PO was cancelled before goods were received.
- Closed — The PO is complete and all related receiving and invoicing has been finalised.
Line items
Each line item on a purchase order represents a specific product or material being ordered. Line items include:
- Product or material — The item being ordered, linked to your product catalogue or materials list.
- Quantity — The number of units requested.
- Unit price — The agreed or expected cost per unit.
- Line total — Quantity multiplied by unit price.
Linking to receiving
When goods arrive from a supplier, you create a Goods Received Note (GRN) linked to the original purchase order. This links the PO to the actual delivery, allowing you to compare what was ordered against what was received. Discrepancies — such as short deliveries or price differences — are flagged automatically.